Build the budget from scope, not square metres alone
Two 1,000 sqm tents can have different costs when eave height, profile, walls, doors, loads, ground and installation scope differ. Ask each supplier to price the same written schedule.

Separate structure, site and service costs
List the structural package, enclosure, doors, floor or civil work, freight, unloading, installation, utilities and optional equipment as separate lines so omissions remain visible.

Use an example layout only as a starting point
The 20 x 50 m format is a planning example, not a pre-approved package. The final design depends on the site, goods, vehicles, operating period and local requirements.